Case studies

Qatoto|Blueprints›Case studies
translate
SearchSigninSign in
🚀 Qatoto is currently in Alpha: the site is incomplete and data may be wiped before launch. Encountered an issue? Let us know.
CreateCreate
HomeHomeBlueprintsBlueprintsStoreStoreR&DR&D

Research and Development

Problem MapProblem MapMarket ResearchMarket ResearchTalentTalentFundingFundingPROJECT IMMORTALPROJECT IMMORTAL

Store

Search the storeSearch the storeCategoriesCategoriesPathwaysPathwaysTrade servicesTrade services

Personalisation

Advertise with usAdvertise with us

Help and settings

Customer serviceCustomer service
How Qatoto WorksAboutPressBlogsContact UsCreatorCareersDevelopersRoadmap
Terms and ConditionsPrivacy PolicyCopyright PolicyCommunity GuidelinesVulnerability Disclosure PolicyPolicies and Safety

© 2026 Qatoto

HomeBlueprintsCreateStoreR&D
SigninSign in
CreateCreate
HomeHomeBlueprintsBlueprintsStoreStoreR&DR&D

Research and Development

Problem MapProblem MapMarket ResearchMarket ResearchTalentTalentFundingFundingPROJECT IMMORTALPROJECT IMMORTAL

Store

Search the storeSearch the storeCategoriesCategoriesPathwaysPathwaysTrade servicesTrade services

Personalisation

Advertise with usAdvertise with us

Help and settings

Customer serviceCustomer service
How Qatoto WorksAboutPressBlogsContact UsCreatorCareersDevelopersRoadmap
Terms and ConditionsPrivacy PolicyCopyright PolicyCommunity GuidelinesVulnerability Disclosure PolicyPolicies and Safety

© 2026 Qatoto

Case studies

What somebody learned the expensive way. Open a lesson to see what they did, or read the full record for the figures and where they came from.

Write a case study
All disciplinesToolingSupply chainQualityDistributionUnit economics
  • Find the step that stopped scaling before you cut the bill of materials.

    Hardware · Porto, 2024 · Unit economics

    Shipped batch four at 512 cents a unit

    Time each assembly step at two volumes before you requote a single component.

    Four production runs of a sensor node. Cost per unit fell 41% between runs one and three, then 3% between three and four, and the team spent two months quoting cheaper parts before they looked at assembly.

    Read the full record→
  • Keep 40% of the raise for batch two.

    Consumer hardware · Chennai, 2023 · Unit economics

    Recovered on batch three, nine months later than planned

    Size batch one so the raise still covers batch two at the same unit cost.

    A cookware brand put its whole seed round into one production run, sold it out in nine weeks, and then could not pay for the second run until the first had collected.

    Read the full record→
  • Budget for a second mould, not a perfect first one.

    Consumer hardware · Nairobi, 2023 · Tooling

    Shipped on the second tool, four months late

    Price the first tool as a prototype you will throw away, and hold the difference for the replacement.

    An injection-moulding programme in Nairobi spent four months and two revisions trying to get one tool right, and shipped six weeks after switching to a cheap tool it expected to replace.

    Read the full record→
  • Cut the tool in aluminium before you cut it in steel.

    Industrial components · Gothenburg, 2024 · Tooling

    Plan the bridge tool into the schedule so the first parts are a test rather than a commitment.

    The same argument as the Nairobi programme, run deliberately rather than by accident: a bracket maker planned two tools from the start and used the first to find eleven changes.

    Read the full record→
  • Qualify the second supplier before you need one.

    Networking hardware · Lagos, 2023 · Supply chain

    Switched assemblers with a seven-week gap in shipments

    Run one paid pilot batch a year with a supplier you are not using.

    A contract assembler went from responsive to unreachable in three weeks. The switch took four months, and three of them were qualification the team could have done a year earlier.

    Read the full record→
  • Order the long-lead part before the design is finished.

    Cold chain · Tunis, 2024 · Supply chain

    List every part over 12 weeks lead time in week one and order the top three on a best guess.

    A compressor with a 22-week lead time set the whole schedule, and the team discovered that four months after freezing everything else.

    Read the full record→