What somebody learned the expensive way. Open a lesson to see what they did, or read the full record for the figures and where they came from.
Networking hardware · Lagos, 2023 · Supply chain
Run one paid pilot batch a year with a supplier you are not using.
A contract assembler went from responsive to unreachable in three weeks. The switch took four months, and three of them were qualification the team could have done a year earlier.
Read the full recordCold chain · Tunis, 2024 · Supply chain
List every part over 12 weeks lead time in week one and order the top three on a best guess.
A compressor with a 22-week lead time set the whole schedule, and the team discovered that four months after freezing everything else.
Read the full record