Order the long-lead part before the design is finished.
List every part over 12 weeks lead time in week one and order the top three on a best guess.
Nadia Haddad
@nadia-cold
Written from the public sources listed below.
A compressor with a 22-week lead time set the whole schedule, and the team discovered that four months after freezing everything else.
Problem
Everything else was ready. The compressor was not, and no amount of engineering effort shortened a 22-week queue at a supplier who had never heard of the company.
Context
A solar cold-storage unit for market traders. Six-person team, first production run of 40 units, working backwards from a harvest season that does not move.
What they did
- Built a lead-time list before the bill of materials was complete, ordered by weeks rather than by cost.
- Placed a deposit on 40 compressors against a specification that was still 80% settled.
- Designed the housing around the compressor that was coming rather than the one that was ideal.
- Negotiated a partial-cancellation clause instead of trying to delay the order.
What to avoid
- The 22-week figure was the supplier's standard quote and turned out to be 31 weeks for a first-time buyer, which nobody asked about.
- Committing early to the compressor forced two housing changes that cost less than the delay would have, but were not free.
The business facts
- Timeline
- One harvest season, 40 units
- Capital raised
- $180,000
- Sahel Cold Systems
- Tunis, 2024
- Quoted lead time, weeks
- 22
- Actual lead time, weeks
- 31
- Units in the first run
- 40